Sorang HEP
"ON GOING DETAILED ENGINEERING SERVICES"
1. | Project Location | Kinnaur District, Himachal Pradesh |
2. | Gross Head | 670 m |
3. | Type of Scheme | Run of the River |
4. | Installed capacity | 2 x 50 = 100 MW |
5. | Type of Turbine | Vertical Pelton Wheel |
6. | Components | Trench Weir, De-Sander Intake, Desilting Basin, HRT (1550m), Surge shaft, Penstock Tunnel, Penstock, Under Ground Power House, Tail Race Tunnel, 400 kV GIS building, Pot head yard and Adits. |
7 | Status | Construction in progress |
8 | Owner | Himachal Sorang Power Ltd., |