Sorang    HEP

"ON GOING DETAILED ENGINEERING SERVICES"

1. Project Location Kinnaur District, Himachal Pradesh
2. Gross Head  670 m
3. Type of Scheme Run of   the River
4. Installed capacity 2 x 50 = 100 MW
5. Type of Turbine Vertical Pelton Wheel
6. Components Trench Weir, De-Sander Intake, Desilting Basin, HRT (1550m), Surge shaft, Penstock Tunnel, Penstock, Under Ground Power House, Tail Race Tunnel, 400 kV GIS building, Pot head yard and Adits.
7 Status Construction in progress
8 Owner Himachal Sorang Power Ltd.,

Projects Photos